Utility undergrounding in La Jolla continues toward 2035 deadline

By Dave Schwab
If you’re wondering how utilities undergrounding is going in Council District 1, which includes much of La Jolla, 14 of the 47 block projects to be constructed between 2004 and 2035 are in the works or have been completed.
Recently finished were Project Block 1F: La Jolla in the Beach-Barber Tract from Neptune Place to La Jolla Boulevard including Vista Del Mar, Monte Vista and Olivetas Avenues, as well as Tyrian Street; and Project Block 1R: University City, which was “christened” recently in a pole removal ceremony attended by First District Councilwoman Sherri Lightner.
San Diego associate traffic engineer Labib Qasem said there are two kinds of utility undergrounding projects — conventional block jobs and arterials, along roadways.
Utilities are being undergrounded for other than visual or aesthetic reasons.
“It’s a safety thing,” Qasem said. “You don’t want these poles to be falling down undoing electrical (service) and communications.”
Through the undergrounding program the city is replacing about 30 to 35 miles of overhead utility lines at an estimated cost of $50 million annually.
Undergrounding has been ongoing since 1970. But in 2003, when the California Public Utilities Commission approved placing an undergrounding surcharge on San Diego residents’ electricity bills, the city has escalated its undergrounding efforts.
Utilities undergrounding involves four phases.
1) City crews create a trench and install round plastic conduit below the surface of the roadway.
2) Cabling, where technicians place new utility lines within the new conduits. The new lines are then energized and brought into service.
3) Cut-overs. Once a new underground system is in place and energized, and all properties have been prepared to receive underground service, all properties are switched over from the overhead lines to the new underground systems, a process typically taking a month or two.
4) Pole removal. After 100 percent of overhead systems have been de-energized and removed and all power has been switched over to the new underground system, the poles come down. There’s also some finishing touches work involved putting in new streetlights, resurfacing roads, etc.

On the Web

• Project Overview: www.sandiego.gov/undergrounding

• Video: http://www.sandiego.gov/undergrounding, then scroll down to the box on the left and click Utilities Undergrounding

Related posts:

  1. Bird Rock students greet 3-day walkers
  2. Scripps Research scientist gets fellowship from Autism Speaks
  3. Design for LJ Shores home wins award
  4. La Jolla church hosting Oaxacan wood carving exhibit, workshop
  5. La Jolla High juniors, Interact ready for rummage sale

Short URL: http://www.lajollalight.com/?p=62088

Posted by Dave Schwab on Apr 10, 2012. Filed under La Jolla, News. You can follow any responses to this entry through the RSS 2.0. You can leave a response or trackback to this entry

Leave a Reply

La Jolla Community Calendar

Facebook

Bottom Buttons 1

Bottom Buttons 2

Bottom Buttons 3

Bottom Buttons 4

Bottom Buttons 5

Bottom Buttons 6

RSS North Coastal News

  • Del Mar Thoroughbred Club releases statement concerning turf course July 27, 2014
    “Del Mar is deeply saddened by the loss of Thoroughbred lives we have experienced at the track since the start of our season. Four of those losses have come on our new turf course. Despite that, we continue to have the utmost confidence in the course, as do our partners in this race meet — the Thoroughbred Owners of California, the California Thoroughbred Tr […]
  • Carmel Valley Library to host piano trio in concert July 27, 2014
    The 45-minute program will include music by Debussy, Schubert, and Dvorak. […]
  • Del Mar residents back from Sports Chalet trip July 27, 2014
    The grand prize included round-trip airfare for two to Kahului Airport, accommodations at the Lumeria Maui, and tickets to OluKai’s annual Ho’olaulea’a concert. […]