Construction at UCSD to yield four new structures in 2012

By Pat Sherman

Four major construction projects at the University of California, San Diego are slated for completion this year, in addition to a $2.1 million facelift of the La Jolla Playhouse grounds.

• Phase II of the Rady School of Management should be finished in April. The $47.2 million, 80,000 square-foot project was funded through $27.1 in state funds and private gifts from Ernest Rady and the Rady Family Foundation, Wells Fargo bank and other sources.

The west campus building, designed by Ellerbe Becket of San Francisco and HMC Architects of San Diego, will feature a 75-seat tiered classroom, two 45-seat instructional flat classrooms, study rooms, conference rooms, a student media room, student support offices, faculty offices, executive classrooms and research areas.

It will also include a 295-seat auditorium to accommodate conferences and student programs, named in honor of Philanthropists Betty and Dr. J Robert Beyster.

The building will be used by faculty and students in the school’s Masters of Business Administration and Doctor of Philosophy programs, as well as business professionals seeking continuing professional education.

The five-story structure will connect with the first phase, also known as Otterson Hall, on four levels. It is expected to receive Leadership in Energy and Environmental Design (LEED) silver certification. Phase I of the Rady School opened in June of 2007.

• Also scheduled for completion in April is the new Southwest Fisheries Science Center laboratory, located on the north side of La Jolla Shores Drive across from Scripps Institution of Oceanography and the existing Southwest Fisheries Science Center.

The $26.1 million project, originally scheduled for completion in December, was delayed due to the magnitude of the development, UCSD officials said.  UCSD is leasing land for the project to the National Oceanic and Atmospheric Administration (NOAA), with which it has a long, collaborative research history.

The 124,000-square-foot structure will contain an experimental aquarium, animal necropsy lab, specimen processing lab, genetic labs, physiology labs, oceanographic labs, specimen archives, electronic workshops and a large tank for testing new sampling technologies, as well as a library, conference rooms and office space for 275 scientists and support staff.

Construction of the facility was paid for in part by American Recovery and Reinvestment Act funds. The original Southwest Fisheries facility is located on the edge of a 200-foot cliff on the coastal side of La Jolla Shores Drive — a site deemed too precarious for long-term use. Removal of three buildings and native plant restoration at the original Southwest Fisheries site will begin in April.

The new building design includes photovoltaic (solar) cells, water retention systems, recycled materials and green roofs planted with California coastal chaparral. It is expected to earn a LEED gold certification.

An artist's rendering of UCSD's new Structural and Nano Materials Engineering Building.

A Marine Ecosystem Sensing, Observation and Modeling Laboratory, slated for completion in May of 2013, will be located across the street from the new Southwest Fisheries building.

• UCSD’s Structural and Nano Materials Engineering Building, located diagonally across from Canyonview Aquatic Center and Warren College, should be complete in August. The $85.2 million project, designed by Safdie Rabines and Miller Hull architects, is funded almost entirely by the state. The 169,000-square-foot project is expected to receive LEED sliver certification. It will provide instruction and research space for the Department of Structural Engineering and the Department of Visual Arts, merging the areas of advanced materials testing with scientific visualization.

• A $26.1 million parking structure at UCSD Medical Center should be complete early this month. The project provides 1,245 parking spaces and a recreation field, under which some of the spaces were constructed.

Roughly $2.1 million in improvements to the campus’s theater district should be finished in June. The project includes the addition of 1,200 square feet onto the existing Mandell Weiss Theatre for a new visitor center. The work will include enhanced signage, simplified pedestrian circulation and improved nighttime lighting, as well as restoration of two acres of grove reserve that lend an identifiable character to the theater district.

A 75,000-square-foot office building on the east campus was completed in October, at a cost of $35.2 million.

Related posts:

  1. Scripps Institution of Oceanography to head $25 million climate research project
  2. Towering crane at fisheries construction site bothers neighbors
  3. Election 2012: Who is Scott Peters?
  4. UCSD student vets salute fallen comrades
  5. Autopsy shows woman found in burning La Jolla car was slain

Short URL: http://www.lajollalight.com/?p=58224

Posted by Pat Sherman on Feb 1, 2012. Filed under Featured Story, La Jolla, News, Region, Schools. You can follow any responses to this entry through the RSS 2.0. You can leave a response or trackback to this entry

Leave a Reply

La Jolla Community Calendar

Facebook

Bottom Buttons 1

Bottom Buttons 2

Bottom Buttons 3

Bottom Buttons 4

Bottom Buttons 5

Bottom Buttons 6

RSS North Coastal News

  • Summer 2014 Carmel Valley Open Basketball League Champs: ‘Carmel Valley Spurs’ August 30, 2014
    On Aug. 18, the Carmel Valley Spurs defeated the Solana Beach Stray Cats, 67-41, in the 5th/6th grade championship game in the Master Sports Carmel Valley OPEN Basketball League. Over a 10-game season, the offense scored 659 points while giving up only 364 on defense. The average game score was 66-36. They had the best rebounders, best shooters, and best def […]
  • Hundreds turn out for Carmel Valley planning board meeting on One Paseo August 30, 2014
    Hearts and visions collided at the Aug. 28 Carmel Valley Community Planning Board meeting, where an overflow crowd turned out to debate the future of the last major slice of the community left to be developed. All 400 seats in Canyon Crest Academy’s theater were filled, and people spilled out into the aisles and crammed into standing-room only spots in the b […]
  • Del Mar Library book-to-movie club picks fall reads August 30, 2014
    Print Goes to the Movies, a book/movie discussion group held at the Del Mar Branch Library at 2 p.m. every second Friday, has announced its upcoming dates and movies. […]